Sequencing and scheduling assist with :: structuring and ordering the transformation process.
Sequencing refers to :: the order in which activities in the operations process occur.
Scheduling refers to :: the length of time activities take within the operations process.
Gantt chart
the primary advantages to Gantt charts:
They force a manager to plan the steps needed to complete a task (& timing)
They make it easy to monitor actual progress against planned activities.
Critical path analysis (CPA)
Critical path analysis (CPA) is :: a scheduling method or technique that shows what tasks need to be done, how long they take and what order is necessary to complete those tasks.
Review Questions: Transformation process
How do sequencing and scheduling differ?
sequencing is the order of activities in the operations process
scheduling is the length of time for said activities